All Saints Church, Terling

All Saints Church, Terling

March 11, 2021 Rachel Finlay Comments Off

To erect the scaffolding pockets were created to take the Haki-beams and corresponding loads upon them. Creating pockets helped to avoid destroying the vestry below to transfer the scaffold load to the ground. Temporary guttering was installed to the base of the spire and remained in place for a year to catch the brown water that runs off the roof initially.

Summary = Conservation and restoration work to All Saints Church in Terling included replacing the oak shingling to the church spire, associated roof timber repairs and masonry repairs to tower. Restoration and re-gilding of clock face and re-gilding to the weathervane.

Value = approximately £105,000

Location = Terling, Essex

Challenge = Temporary guttering had to be installed to the base of the spire for a year, to let rainwater wash the tannin out of the new oak shakes without discolouring the church tower.

Solution = To erect the scaffolding pockets were created to take the Haki-beams and corresponding loads upon them. Creating pockets helped to avoid destroying the vestry below to transfer the scaffold load to the ground.

Temporary guttering was installed to the base of the spire and remained in place for a year to catch the brown water that runs off the roof initially. This is caused by the oak ‘tannin’ that comes of the oak shakes and will decrease over time once washed out by the rain. Rodells Steeplejacks later removed guttering and downpipe.

Conservation and Restoration Work to the Spire

Conservation and restoration work to the spire at All Saints Church involved stripping the cedar shingles for the full height of the spire and carrying out timber roof repairs. A handful of re-connections of timber joints were installed, where structural heave had caused an oak dowel to fail in the joint, resulting in partial separation of the timbers. These were tied back together with a piece of stainless-steel strapping. All battens were placed with treated softwood and new oak shakes were installed.

The new shakes installed were split, not sawn. Shingles are sawn, whereas shakes can be split, split and sawn or simply sawn, depending on the type of grade required.

Stone Repairs and Replacement

Stone repairs were carried out, and the eroded existing stone quoins were cut out and replaced with new Hartham-Park stone quoins. Open joints in the brickwork were repointed. Tom Poysner who was at the time taking part in block release training at Stratford Crafts college to become a Banker Mason, predominantly fitted the replacement stone quoins along with another experienced Mason. A Banker Mason carries out the final preparation work on stone-masonry blocks by hand.

Conservation and Restoration Work to the Weathervane, Clock Face and Sundial.

The weathervane was removed, repaired, decorated and re-gilded. The existing lightning conductor tape was replaced with new.

A Specialist gilder/decorator bought the stone clock and sundial back to life by restoring and re-gilding them. The name “Rocky the Rocket” was given to the weathervane due to his strange appearance, as he looks like he has rockets strapped to his sides!