Benyon Primary School, Thurrock

New build school extension

Benyon Primary School, Thurrock

November 12, 2020 Rachel Finlay Comments Off

The new build school extension provided six new classrooms, which were handed over to the school to occupy, whilst Bakers refurbished four existing classrooms. The extension was mainly single storey, with a high roof where it extends the existing main hall. The extension had a block and beam floor and a hollowcore plank roof

Summary = A new build school extension comprising of six classrooms including alteration and refurbishment works within the existing school, and extensive hard landscaping to extend the car park and playground.

Value = £1,730,000

Location = Thurrock, Essex

Challenge = Due to the National Lockdown which was put place to stop the spread of covid-19; it was decided to reprogram the project, after close consultation with the school and Thurrock council.

Solution = The new build school extension provided six new classrooms, which were handed over to the school to occupy, whilst Bakers refurbished four existing classrooms. The extension was mainly single storey, with a high roof where it extends the existing main hall. The extension had a block and beam floor and a hollowcore plank roof, finished with Sarnafill which is a single ply roofing membrane for flat roof waterproofing. Refurbishment works currently taking place include the main hall, corridors, staffroom, reception and administration areas. The project is set to meet its deadline of the 31st December 2020.

Some existing windows and doors were refurbished, together with new windows and DF30 and DF60 fire rated doors installed. An external automatic fire door was installed to the main hall to provide an exit to outside. Joinery works include a new reception desk with an oak and glazed glass reception screen. New timber glazed screens were manufactured and installed within the reception and the main hall. New door linings and frames in soft wood were manufactured and installed to the reception area and the new extension.

Temporary works included installing a hardcore lane, leading from the existing school gate within the school field to the site compound, all of which were securely fenced off from the school field and playground. As the only entrance is off Tyson Place, all parking and deliveries took place during designated times out of school pick-up, drop-off and breaks. To help manage this, deliveries had to call the site office before arrival.

The existing car park was extended to provide extra hard surface parking spaces and modifications made to collect surface water from the car park. The existing playground was remodelled and resurfaced as well as extended to provide a new playground. New rainwater goods were installed to the extension, and modifications to the foul and service water made to the existing building. Landscaping is programmed to take place during the October half term. A new canopy is currently being constructed to the main entrance, with a block column, roof joists and cladded in traspar cladding to match exiting cladding throughout the school. Bakers are currently constructing a metal cycle shelter which was manufactured offsite, to be later constructed onsite and fixed on a concrete base.

As the project was considered as essential works, it continued throughout the National lockdown. Although works were carried out whilst the school was closed, Bakers had to ensure that the school remained fully functioning because for many months, it was not clear as to when the school will reopen. After consulting the school and Thurrock Council, it was agreed that Bakers would bring forward the refurbishment and alteration works to the corridors, main hall and the new car park extension, which were originally programmed to take place during school holidays.

To continue works during the lockdown Bakers implemented a new risk assessment to ensure social distancing and other measures were introduced to prevent the risk of spread of Covid-19 amongst everyone working on the project. Throughout the project, monthly progress review meetings have been taking place remotely with Bakers’ Contract Manager and Site Manager, Architect, Thurrock Council and the school.

It has been extremely important that Bakers works closely with the school to manage access and safety issues, particularly when carrying out refurbishment works to within the school after the students returned after lockdown. The site is always monitored by the Site Manager and inspections carried out by our external health and safety consultant to ensure we comply with health and safety legislation.