Roof works and internal decoration to Sawston Village College

roof works and internal decoration college building

Sawston Village College

October 3, 2019 Rachel Finlay Comments Off

The project was divided into two phases and temporary roofs protected the Grade II Listed Henry Morris building during Phase one and the North Wing during Phase two of works. Phase one of works to Sawston Village College, an academy school founded in 1930, began April 2019.

Summary = Roof works and internal decoration to two college buildings

Location = Cambridgeshire

Challenge = The Grade II Listed buildings had to be protected from the weather whilst the roofs were stripped and replaced

Solution = The project was divided into two phases and temporary roofs protected the Grade II Listed Henry Morris building during Phase one and the North Wing during Phase two of works.

Phase one of works to Sawston Village College, an academy school founded in 1930, began April 2019. Works involved the installation of the temporary roof whilst the stripping and re-roofing of the Grade II Listed Henry Morris building took place. The existing pantiles were re-laid to the front elevation of the building and new handmade pantiles were installed to the back.

Below the roof, the deteriorating lath and plaster ceiling to the main hall was replaced with new, which included the installation of new laths, scratch coat and a finish of thermalime plaster previously approved by the Conservation Officer. Existing facia boards were replaced and the cast iron gutters and downpipes were thoroughly sanded back to metal and painted. The bell tower underwent extensive repairs to the leaded lights, structural timber and boarding.

The second phase of works included roof works to the North Wing of the College, similar to the roof works to the Henry Morris building. All roof works and internal decoration was completed in time to hand back to the College for the new Academic New Year.