Bakers of Danbury were appointed as the principal contractors for the design and build of a new teaching block at a school in Essex.This included 3 classrooms, staff room, teaching areas, hygiene area,

May 14, 2024 Comments Off

Bakers of Danbury, Church Department, have completed works to the beautiful Grade 1 listed church of St Peter's in Henley, Ipswich. The objective of the works was to carry out an internal re-ordering

April 12, 2024 Comments Off

Bakers of Danbury have completed a programme of repair to resurrect a beautiful Grade II listed farmhouse in Suffolk. As a listed building, the project required building methods and materials that were suitable

April 9, 2024 Comments Off

Colchester Cemetery Chapel is a historic Anglican cemetery chapel with a history spanning 160 years. Understood to have been constructed in 1855, the chapel had become derelict over recent years. With Colchester Borough

November 27, 2023 Comments Off

Bakers of Danbury commenced work in July 2023 to carry out essential restoration works to this 12th Century Grade I listed church situated in Kingston in Cambridge.  Features of special interest include the

July 6, 2022 Comments Off

Bakers of Danbury recently carried out a refurbishment at Witham Fire Station which included two classrooms and an office. Chrysotile asbestos was removed from the ceilings of the classrooms before works began. Works

November 4, 2021 Comments Off

The 42 week refurbishment and new build extension project consisted of two phases with individual projection completion and sign off dates for handover. Both phases were completed to deadline and within contract sum.

March 9, 2021 Comments Off

As principal contractor Bakers of Danbury recently completed a new build extension to provide a new classroom extension to Grays Convent School. The single classroom extension was constructed from a block and brick,

November 12, 2020 Comments Off

The new build school extension provided six new classrooms, which were handed over to the school to occupy, whilst Bakers refurbished four existing classrooms. The extension was mainly single storey, with a high

February 18, 2020 Comments Off

Westminster School is the only ancient school in London which still occupies its original site. The site of the new extension is very closely surrounded by Grade I Listed buildings, some dating back

October 10, 2019 Comments Off

Enabling works to Chelmsford County High School for Girls ahead of the construction of a new Sports Hall and teaching block, which will include additional science facilities, Enabling works to Chelmsford County High

October 3, 2019 Comments Off

The project was divided into two phases and temporary roofs protected the Grade II Listed Henry Morris building during Phase one and the North Wing during Phase two of works. Phase one of

August 16, 2017 Comments Off

Delivery times were restricted so that deliveries did not take place during school pick up or drop off times. Works stopped whilst the pupils sat their SAT exams. As principal contractor, Bakers of